Conductor Material Required in Underground 1-Phase 2-Wire AC System with Mid-Point Earthed
Conductor Material Required in Underground 1-Phase 2-Wire AC System with Mid-Point Earthed
Figure-2 shows the underground single-phase two-wire AC system with mid-point earthed.

Here,
Thus, the load current is given by,
If 𝑎2 is the cross-section area per conductor and R2 is the resistance per conductor. Then, the total power loss in the line conductors is
Hence, the volume of conductor material required in the underground single-phase two-wire AC system with mid-point earthed, say K1, is given by,
Hence, from equations (1) and (2), it is clear that the volume of conductor material required in the 1-phase 2-wire underground AC system with mid-point earthed is same as that required for the 1-phase 2-wire underground AC system.